2026 Chattanooga, TN PressurePave

COMPLETED

Chattanooga, TN

Please anticipate delays as roads will be periodically closed throughout the day. An orange or yellow cone in your driveway indicates that work is scheduled for your road next; when moved to the center, it signifies that fresh oil is present. The material typically dries in 30 minutes but may take up to 2 hours to fully cure—please refrain from driving or turning around on it. Turn off irrigation systems on scheduled dates and keep them off for 24 hours after the work is complete. Inform any lawn care, cleaning, or contractor services about the upcoming work. All vehicles must be removed from the roadway; any vehicles left during construction will be towed. No overnight parking is permitted after your road is completed. Avoid turning your wheels while stationary on fresh material to prevent damage. Crews will begin work around 7:30 a.m. with street preparation and will start laying material around 8:00 a.m., finishing by 8:00 p.m. Traffic coordinators will be present to direct vehicles and answer any questions.

Start Date

July 27, 2026

End Date

July 31, 2026

Donelson Construction will begin road resurfacing work for the City of Chattanooga, TN PLEASE NOTE: THE EXACT ORDER OF OPERATIONS MAY CHANGE DAILY DUE TO WEATHER AND ON-SITE CONDITIONS. We encourage residents to check back frequently for updates and appreciated your continued patience and cooperation as we work to improve your streets.

Project Location

Chattanooga, TN

Map Legend
Green - Completed
Different colored lines and shapes represent various project phases and their current status.
AI

Get instant answers about this project's schedule, streets, and progress. Answers come from the project's own details, map, and updates.

AI answers are based only on this project's posted information and may not reflect last-minute changes. For anything urgent, contact the construction team.
Updates
Jul 31, 2026 at 11:48 AM by Donelson Construction

Resurfacing will begin around 8:00 a.m. this morning for Brynwood Dr

Jul 30, 2026 at 06:30 PM by Donelson Construction

Crew will get spot repairs done today on Brywood Dr but will have to finish up Friday on the final surface

Jul 30, 2026 at 12:13 PM by Donelson Construction

Resurfacing will begin around 8:30 a.m. for the Highview Dr cul-de-sacs and Brywood Terrace

Jul 29, 2026 at 10:19 PM by Donelson Construction

Crew was only able to do spot repairs on Brywood Ter. today. Crew will begin tomorrow 7/30/26 in Highview Dr cul-de-sac area's first then move over to Brywood Ter and pull one lane. They will move back to cul-de-sac roads and work there way out to Oak Tree Dr. Once completed they will finish second lane of Brywood Terr. Crew will finish off day doing spot repairs on Brywood Dr and if time allows do some Production pulls.

Jul 29, 2026 at 08:13 PM by Donelson Construction

All roads in the Green Zone have been completed

Jul 28, 2026 at 09:30 PM by Donelson Construction
Status: Planned

we wil work on Anna and Highlandway (Green Zone) first thing tomorrow morning. once that's complete we will start spot repairs in the red zone thru out the whole area so please have vehicles off the road so we can clean and prep. If time still allows late afternoon we will lay material on Brywood Terr.

Jul 28, 2026 at 02:06 PM by Donelson Construction

Resurfacong will begin around 9:15 for the Orange roads in the Green Zone

Jul 28, 2026 at 01:07 PM by Donelson Construction

Resurfacong will begin around 9:15 for the Orange roads in the Green Zone

Jul 27, 2026 at 09:08 AM by Donelson Construction
Status: Planned

Crew will be out today 7/27/26 to do grass removal and prep road for tomorrow's work.

Jul 19, 2026 at 09:33 PM by Donelson Construction

Once again with uncertain weather conditions we will have to unfortunately push back the project another week.

Jul 12, 2026 at 04:51 PM by Donelson Construction

With current weather forecast we will have to move the project to the week of the 20th of July weather permitting.

Jul 05, 2026 at 04:00 PM by Donelson Construction

We had planned for the week of July 6th to begin our project but unfortunately once again the weather is not favorable so will push off one more week beginning July 14th.

Jul 05, 2026 at 04:00 PM by Donelson Construction

We had planned for the week of July 6th to begin our project but unfortunately once again the weather is not favorable so will push off one more week beginning July 14th.

Jun 26, 2026 at 04:16 PM by Donelson Construction
Status: Planned

Weather looking good for resurfacing project to begin the week of July 6th .

Jun 07, 2026 at 06:42 PM by Donelson Construction

Due to rain chances the week of the June 8th we will postpone project to the week of June 15th

Jun 07, 2026 at 06:42 PM by Donelson Construction

Due to rain chances the week of the June 8th we will postpone project to the week of June 15th

Jun 01, 2026 at 08:18 PM by Donelson Construction
Status: Planned

Work is scheduled to begin June 9th (weather permitting). Please help the construction effort by moving any parked cars off the street and turning off sprinkler systems until construction is complete (hopefully June 11). Thank you in advance! For more info about the PressurePave process visit: https://www.youtube.com/@donelsonconstructioncompan5298

Project Information
Construction Company

Donelson Construction

Create account to message contractor
Overseeing Agency

City of Chattanooga Public Works

Create account to message agency
Project Progress
Project Code
QR Code for Project

Scan to view project details

Download QR Code