Waxahachie, Texas PressurePave

COMPLETED

Waxahachie, Texas

Please expect delays as roads will be periodically closed throughout the day. A cone in your driveway indicates that fresh oil is present. If you require assistance while a cone is in place, please speak with a Flagger or contact the Traffic Control Supervisor. Material typically dries in 30 minutes but may take up to 2 hours to fully cure; therefore, please avoid driving or turning around on it. Turn off irrigation systems on scheduled dates and keep them off for 24 hours after work is completed. Notify any lawn care, cleaning, or contractor services about the work. All vehicles must be removed from the roadway; any vehicles left during construction will be towed. No overnight parking is allowed after your road is completed. To prevent damage, avoid turning your wheels while stationary on fresh material. Crews will begin work around 7:30 a.m., starting in cul-de-sacs and moving to main streets, finishing around 6:00 p.m. Traffic coordinators will be present to help direct vehicles and answer questions. Please move basketball goals off the street or curb. Josie McFall, Traffic Control Supervisor 417-536-3799 M-F 8 AM - 5 PM

Start Date

May 26, 2026

End Date

June 12, 2026

Donelson Construction will begin road resurfacing work for the City of Waxahachie PLEASE NOTE: THE EXACT ORDER OF OPERATIONS MAY CHANGE DAILY DUE TO WEATHER AND ON-SITE CONDITIONS. We encourage residents to check back frequently for updates and appreciated your continued patience and cooperation as we work to improve your streets. Due to weather, we will be postponing this project until the week of June 8th and should be completed June 12th

Project Location

Waxahachie, Texas

Map Legend
Green - Completed
Different colored lines and shapes represent various project phases and their current status.
Updates
Jun 11, 2026 at 04:43 PM by Donelson Construction Company
Status: In Progress

We have completed Fordyce Circle, Drexal Drive, and Lexington. One lane of Vermont is finished, and we have now begun work on Peters. We expect to complete the remaining lanes very soon.

Jun 10, 2026 at 07:08 AM by Donelson Construction Company
Status: In Progress

We have completed all work in the red zone, and all parking areas and roads in that zone are now open. We will begin work in the purple zone on Thursday morning. Please ensure that all vehicles are removed from the roadway to facilitate a swift completion of these roads. We aim to finish the work on Thursday.

Jun 10, 2026 at 07:08 AM by Donelson Construction Company
Status: In Progress

We have completed all work in the red zone, and all parking areas and roads in that zone are now open. We will begin work in the purple zone on Thursday morning. Please ensure that all vehicles are removed from the roadway to facilitate a swift completion of these roads. We aim to finish the work on Thursday.

Jun 09, 2026 at 03:08 AM by Donelson Construction Company
Status: In Progress

All street parking in the red zone will remain closed until Wednesday morning. We plan to complete work in the red zone by Tuesday night. To protect the fresh material, we must keep this area closed until the roads are finished. We apologize for any inconvenience this may cause and appreciate your patience as we work to complete and reopen these roads as quickly as possible. For further assistance, please contact Josie McFall, the Traffic Control Supervisor, at 417-536-3799. Thank you for your understanding.

Jun 09, 2026 at 03:08 AM by Donelson Construction Company
Status: In Progress

All street parking in the red zone will remain closed until Wednesday morning. We plan to complete work in the red zone by Tuesday night. To protect the fresh material, we must keep this area closed until the roads are finished. We apologize for any inconvenience this may cause and appreciate your patience as we work to complete and reopen these roads as quickly as possible. For further assistance, please contact Josie McFall, the Traffic Control Supervisor, at 417-536-3799. Thank you for your understanding.

Jun 08, 2026 at 02:17 PM by Donelson Construction Company
Status: Planned

We will begin work in the red zone tonight at 6 PM. Please remove all vehicles from the road to allow us to complete this area as quickly as possible. Work will start on all parking areas tonight, and we will also address the Main Street areas tonight and tomorrow night. For further assistance, please contact Josie McFall, the traffic control supervisor, at 417-536-3799.

Jun 01, 2026 at 09:25 PM by Donelson Construction
Status: In Progress

Due to weather conditions, we will resume work during the week of June 8th.

May 21, 2026 at 06:21 PM by Donelson Construction
Status: In Progress

Due to inclement weather, we will be postponing the project until the week of June 1st. Enjoy Memorial Day!

Update image
May 15, 2026 at 01:17 AM by Donelson Construction Company
Status: In Progress

We have completed the blue and green zones. Due to the forecasted weather for next week, we will not be able to work on the remaining two zones until conditions improve. Our plan is to return from May 26th to May 29th to complete the remaining roads. The purple zone will be addressed during the day, while the red zone will be worked on during overnight hours. Please stay tuned for further updates, as we will provide new information here. We apologize for any inconvenience and hope for improved weather so we can resume work on this project soon.

May 15, 2026 at 01:17 AM by Donelson Construction Company
Status: In Progress

We have completed the blue and green zones. Due to the forecasted weather for next week, we will not be able to work on the remaining two zones until conditions improve. Our plan is to return from May 26th to May 29th to complete the remaining roads. The purple zone will be addressed during the day, while the red zone will be worked on during overnight hours. Please stay tuned for further updates, as we will provide new information here. We apologize for any inconvenience and hope for improved weather so we can resume work on this project soon.

May 13, 2026 at 11:36 PM by Donelson Construction Company
Status: In Progress

Due to an unexpected delay, we will not be able to complete the Sycamore project this evening. We will return first thing tomorrow to finish the road. We apologize for any inconvenience this may have caused.

May 13, 2026 at 08:01 PM by Donelson Construction Company
Status: In Progress

We will finish work on Sycamore this afternoon and evening. We have completed two of the green zones and will work on the last one, The River Oaks subdivision, tomorrow. Additionally, we plan to start in the purple zone tomorrow. Please remove any vehicles from the roadway to facilitate a swift completion of the streets.

May 12, 2026 at 10:23 PM by Donelson Construction Company
Status: Planned

We have completed the majority of the green zone today. We will finish the remaining work on Sycamore in the morning. Please ensure that any vehicles on Sycamore are removed this evening to allow us to complete the road without the need to tow any vehicles.

May 12, 2026 at 02:02 PM by Donelson Construction Company
Status: Planned

We will be working in the green zones today. Please remove any vehicles parked in the roadway to allow us to complete your street as quickly as possible. If you need assistance, please call the number provided or feel free to approach any crew members you see.

Project Information
Construction Company

Donelson Construction Company

Create account to message contractor
Overseeing Agency

No overseeing agency specified

Create account to message agency
Project Progress
Project Code
QR Code for Project

Scan to view project details

Download QR Code