Welcome! You're viewing this project as a guest.
Create an account to follow projects, rate contractors, and receive updates.
Lincoln, Nebraska Pressure Pave 2026
Lincoln, Nebraska
Expect delays. Roads will be periodically closed throughout the day. Schedule - Crews begin around 7:30 a.m., starting in cul-de-sacs and moving to main streets, and typically finish around 6:00 p.m. - Traffic coordinators will be on site to direct vehicles and answer questions. Driveways and fresh material - A cone placed in your driveway indicates fresh oil. If you need assistance while a cone is in place, contact a Flagger or the Traffic Control Supervisor. - Material typically dries in 30 minutes but may take up to 2 hours to fully cure. Do not drive on or turn around on fresh material. To prevent damage, avoid turning your wheels while stationary on fresh material. Irrigation and services - Turn off irrigation systems on the scheduled dates and keep them off for 24 hours after work is completed. - Notify any lawn care, cleaning, or contractor services about the work. Parking and property - Remove all vehicles from the roadway; vehicles left during construction will be towed. - No overnight parking is allowed after your road is completed. - Please move basketball goals off the street or curb. Josie McFall, Traffic Control Supervisor 417-536-3799 M-F 8:00 a.m. – 5:00 p.m.
Start Date
July 06, 2026
End Date
July 31, 2026
Donelson Construction will begin road resurfacing work for the City of Lincoln PLEASE NOTE: THE EXACT ORDER OF OPERATIONS MAY CHANGE DAILY DUE TO WEATHER AND ON-SITE CONDITIONS. We encourage residents to check back frequently for updates and appreciated your continued patience and cooperation as we work to improve your streets This is our plan for the zones we will be working in on each workday. Our workdays are Monday through Friday. Please check back often for updates, as this plan may change due to circumstances that arise in real time. We will do our very best to follow this schedule. Day 1-2 Red zone 7/7-7/8 Day 2-3 Green zone 7/7-7/8 Day 3-5 Orange zone 7/9-7/10 & 7/13-7/15 Day 5-6 Purple zone 7/13-7/17 Day 7-9 Blue zone 7/15-7/17 & 7/20-7/24
Project Location
Lincoln, Nebraska
Map Legend
Streets in this work zone (128)
84th Street Trail, Alamosa Drive, Andrew Court, Ashlee Lane, Avon Lane, Bartholomew Circle, Baxter Place, Berkeley Drive, Blue Sky Drive, Branford Place, Browning Street, Brummond Drive, Cactus Court, Canyon Road, Chisholm Place, Chisholm Road, Collister Road, Coronado Drive, Davenport Circle, Davenport Drive, Daybreak Circle, Daybreak Drive, Denver Court, Duane Lane, Durango Court, Earl Drive, East Avon Lane, Eastview Road, El Avado Avenue, Fieldcrest Way, Gate 1, Gettysburg Drive, Heumann Drive, Holdrege Street, Hollywood Avenue, Horizon Drive, Katelyn Circle, Katelyn Lane, Kendra Lane, La Brea Avenue, Lambert Place, Laredo Drive, Larson Boulevard, Lawson Drive, Linwood Lane, Lone Tree Circle, Lone Tree Drive, Mahoney Drive, Morning Glory Lane, Nogales Circle, Norman Road, North 48th Street, North 53rd Street, North 54th Street, North 55th Street, North 56th Street, North 57th Street, North 58th Street, North 59th Street, North 80th Street, North 86th Street, North 87th Street, North 88th Street, North 92nd Street, North 96th Street, North 98th Street, O Street, O'Malley Circle, O'Malley Drive, Odessa Court, Old Cheney Road, Old Farm Court, Old Farm Road, Orchard Street, Pecos Road, Pine Lake Road, Porter Circle, Porter Ridge Road, Pueblo Court, Ridge Line Road, Rolling Hills Boulevard, Rolling Hills Court, Saint Andrew's Place, Saint Michaels Road, Santa Monica Avenue, Sawyer Street, Saybrook Lane, Sedalia Circle, Sedalia Drive, Sierra Drive, Sissel Road, Sonora Court, South 14th Street, South 19th Street, South 21st Street, South 27th Street, South 28th Street, South 29th Circle, South 29th Street, South 30th Place, South 30th Street, South 31st Street, South 32nd Street, South 34th Court, South 34th Street, SouthPointe Trail, Southern Sky Road, Sunbeam Lane, Sunny Slope Road, Sunridge Road, Tamarin Ridge Road, The Knolls, Thunder Bay, Trail Ridge Road, Trenridge Way, Vegas Road, Vine Street, Whitlock Place, Whitlock Road, Williamsburg Drive, Wilshire Boulevard, Winding Ridge Court, Winding Ridge Road, Woodstock Avenue, Woodstock Circle, X Street, Y Street, Yuma Lane
Street names are generated from the project's map and update when the map changes. For phase-by-phase status, use the "Ask About This Project" section below.Get instant answers about this project's schedule, streets, and progress. Answers come from the project's own details, map, and updates.
Updates
We have now completed work on all roads and in all neighborhoods. Thank you for your patience and cooperation.
Now that the rain has passed, we will begin resurfacing the remaining roads in the order posted earlier. Please turn off your sprinklers today and do not park on the roads listed.
With rain in the forecast, we are unsure when work will resume. When it does, we will complete the remaining roads in this order: - Porter Ridge- Sisseel,Collister Loop - 29th - Whitlock Please keep all vehicles removed from these roads so we can finish as quickly as possible. We experienced several delays yesterday due to vehicles on the roads, so park in your driveway or on a street that has already been completed.
We will be resurfacing today and hope to finish tomorrow if all goes according to plan. Work will follow the order below; we may be working on one lane or several lanes at a time. This schedule is subject to change if problems arise, but we will do our best to adhere to the sequence: - 30th - 32nd - Brummund - Katelyn - Sissel/Collister, Porter ridge Loop - 29th - Whitlock
Today we will resurface Porter Ridge from 27th to Porter Ridge, then resurface 29th from 27th to Porter Ridge. These sections will be completely closed while work is in progress and will be reopened as soon as they are completed.
Due to rain, no work will be performed today, tomorrow, or Friday. Work will resume on Monday, 7/27.
We will begin work in the Porter Ridge Subdivision this morning. We will start with the cul-de-sacs and work on additional streets this afternoon. After completing the cul-de-sacs, we will finish the remaining roads in the Southern Hills Subdivision; we plan to complete Southern Hills today. Please remove all vehicles from the roadway.
We will begin work on the remaining roads in the Southern Hills subdivision soon. Please remove all vehicles parked on the streets scheduled for resurfacing.
We completed 28th and 30th, along with the previously listed roads, today. We will return Monday afternoon to continue work in the Southern Hills subdivision.
Today we will work on Coronado, Alamosa, and Sedalia in the Southern Hills subdivision. We will return Monday afternoon to continue work in Southern Hills. We expect to complete Southern Hills on Tuesday, after which we will start in the Blue Zone (Porter Ridge subdivision), our final zone.
Due to the increased chance of rain, we will not be able to continue work in the Southern Hills Subdivision this evening. We will return tomorrow morning to resume resurfacing the remaining roads. Please remove all vehicles from the roadway by 7:00 AM tomorrow. We have now completed the Rolling Hills Subdivision.
Today we will be in the Southern Hills Subdivision beginning road work throughout the neighborhood. Please turn off all sprinklers and remove all vehicles from the roadway. Expect delays; thank you for your patience and understanding. We expect to finish Rolling Hills Boulevard sometime today. Please ensure all vehicles are removed so we can complete that neighborhood.
We are finishing up in the Rolling Hills subdivision for the night. We were not able to complete the work there and will finish it tomorrow, so please remove all vehicles from the roadway on Rolling Hills tomorrow. Tomorrow we will be working on roads throughout the Southern Hills subdivision. Please turn off all sprinklers for the day and remove vehicles from the roadway.
Resurfacing in the Southern Hills subdivision will begin tomorrow morning. Crews will start on the cul-de-sacs, then return to the Rolling Hills subdivision to complete the remaining roads. Please remove all vehicles from the roadway and turn off all sprinklers. If you have scheduled services (tree removal, lawn care, or any work that requires equipment or vehicles in the roadway), contact Josie McFall at 417-536-3799 to discuss whether the work can proceed or needs to be rescheduled. Thank you for your cooperation and patience.
Today we will be resurfacing streets throughout the Rolling Hills Subdivision (Orange Zone). Work will begin this morning in the cul-de-sacs. Please remove all vehicles from the roadway so we can complete the neighborhood as quickly as possible. We plan to be in your neighborhood today and tomorrow; delays are expected. For assistance, please call Josie McFall at 417-536-3799. We appreciate your cooperation and patience.
We were unable to complete Winding Ridge Road this evening. We will return tomorrow morning to begin resurfacing in the cul-de-sacs, then continue on the other roads throughout the neighborhood. Please remove all vehicles from the roadway.
We will begin work today in the Rolling Hills subdivision. Crews will be resurfacing Field Crest Way, St. Michael’s Road, South 19th Street, and Winding Ridge Roads. Please remove all vehicles from the roadway to allow us to complete the work as quickly as possible. If you need assistance, call Jose McFall at 417-536-3799. We will be working on the cul-de-sacs tomorrow morning, along with many other roads in the neighborhood. We expect to finish on or by Wednesday. Please check here frequently for updates, as this is the best way to receive the most up-to-date information.
Due to changing rain chances, we will not be able to work on the cul-de-sacs today. We will return Monday to resume work for the week.
We have completed the Hollywood Hills subdivision (Green Zone). This morning we will work on the cul-de-sacs in the Rolling Hills subdivision (Orange Zone). We will return Monday afternoon and continue work next week in the remaining areas.
Due to wet conditions this morning, we were unable to complete the cul-de-sacs in the Rolling Hills subdivision and will not be working there today. We will finish the Hollywood Hills subdivision today and, weather permitting, complete the Rolling Hills cul-de-sacs tomorrow morning.
We will begin resurfacing in the Rolling Hills subdivision this morning. Crews will start in the cul-de-sacs, then return to Hollywood Heights this afternoon to complete the remaining roads. Please remove all vehicles from the roadway so we can finish as quickly as possible. For assistance, call Traffic Control Supervisor Josie McFall at 417-536-3799 or speak with any crew member. Thank you for your patience.
We have completed work at Sunrise Estates and will begin resurfacing in the Hollywood Heights subdivision. Please move all vehicles off the roadway. If you need assistance, stop any crew member or call the Traffic Control Supervisor, Josie McFall, at 417-536-3799.
Today we will finish work in the Sunrise Hill estate Subdivision and begin resurfacing in the Hollywood Heights and Park Valley Heights Subdivisions. Please move all vehicles off the roadway so we can finish here as quickly as possible. There will be delays; please be patient. If you need assistance, ask any crew member or call Josie McFall, Traffic Control Supervisor, at 417-536-3799.
Resurfacing of the Sunrise Estates/Hills subdivision will begin this morning and is expected to be completed tomorrow afternoon. If you need assistance, please stop any crew member or call Traffic Control Supervisor Josie McFall at 417-536-3799. Please remove all vehicles from the roadway so the work can be completed as quickly as possible. There may be delays; we appreciate your patience and understanding.
Project Information
Construction Company
Donelson Construction Company
Create account to message contractorOverseeing Agency
Lincoln Transportation & Utilities
Create account to message agency