Springfield, MO PressurePave Project

IN PROGRESS

Springfield, MO

Please expect delays as roads will be periodically closed throughout the day. A cone in your driveway indicates that fresh oil is present. If you require assistance while a cone is in place, please speak with a Flagger or contact the Traffic Control Supervisor. Material typically dries in 30 minutes but may take up to 2 hours to fully cure; therefore, please avoid driving or turning around on it. Turn off irrigation systems on scheduled dates and keep them off for 24 hours after work is completed. Notify any lawn care, cleaning, or contractor services about the work. All vehicles must be removed from the roadway; any vehicles left during construction will be towed. No overnight parking is allowed after your road is completed. To prevent damage, avoid turning your wheels while stationary on fresh material. Crews will begin work around 7:30 a.m., starting in cul-de-sacs and moving to main streets, finishing around 6:00 p.m. Traffic coordinators will be present to help direct vehicles and answer questions. Please move basketball goals off the street or curb. Josie McFall, Traffic Control Supervisor 417-536-3799 M-F 8 AM - 5 PM

Start Date

September 08, 2026

End Date

October 02, 2026

Donelson Construction will begin road resurfacing work for the City of Springfield PLEASE NOTE: THE EXACT ORDER OF OPERATIONS MAY CHANGE DAILY DUE TO WEATHER AND ON-SITE CONDITIONS. We encourage residents to check back frequently for updates and appreciated your continued patience and cooperation as we work to improve your streets

Project Location

Springfield, MO

Map Legend
Blue - Planned
Purple - In Progress
Orange - Scheduled Next
Red - Delayed
Green - Completed
Different colored lines and shapes represent various project phases and their current status.

Streets in this work zone (43)

Crighton Place, East Bennett Street, East Bentree Place, East Blaine Street, East Blueridge Street, East Calhoun Street, East Carol Drive, East Central Street, East Country Place, East Eastwood Boulevard, East Kingsbury Street, East Linwood Drive, East Linwood Terrace, East Locust Street, East Lynn Street, East Meadowmere Place, East Pacific Street, East Portland Street, East Stanford Street, East Sunshine Street, East Webster Street, East Whitehall Drive, Lovers Lane, North Benton Avenue, North Clay Avenue, North Hampton Avenue, North Sherman Avenue, North Summit Avenue, North Texas Avenue, North Washington Avenue, Schoolcraft Freeway, South Abbey Road, South Augusta Avenue, South Bedford Avenue, South Black Locust Place, South Charing Road, South Devon Road, South Eastgate Avenue, South Jones Mill Lane, South Oakmont Avenue, South Ranch Drive, South Summer Place, Woodbury

Street names are generated from the project's map and update when the map changes. For phase-by-phase status, use the "Ask About This Project" section below.
AI

Get instant answers about this project's schedule, streets, and progress. Answers come from the project's own details, map, and updates.

AI answers are based only on this project's posted information and may not reflect last-minute changes. For anything urgent, contact the construction team.
Updates
Sep 11, 2026 at 02:22 PM by Donelson Construction Company
Status: In Progress

We will be unable to finish the red zone today. Today we will complete only Calhoun, from Benton to Clay. We will return on Monday to complete the remainder of the red zone.

Sep 10, 2026 at 03:46 PM by Donelson Construction Company
Status: In Progress

We hope to complete the red zone tomorrow and begin resurfacing in the green zone on Monday, starting with cul-de-sac roads.

Sep 10, 2026 at 11:16 AM by Donelson Construction Company
Status: In Progress

Due to the rain forecast for today, we will not be resurfacing. Crew members will be on site performing grass removal and posting in the green zone.

Sep 08, 2026 at 11:36 PM by Donelson Construction Company
Status: In Progress

We completed Blaine, Locust, and Hampton today.

Sep 08, 2026 at 11:35 PM by Donelson Construction Company
Status: In Progress

Resurfacing will begin on Washington, Summit,pacific and Clay tomorrow morning. If those streets are not completed tomorrow, we will finish the remaining work Thursday if weather permits; if it rains, completion will occur Friday. If weather permits on Thursday, we will begin resurfacing Lynn, Calhoun, Webster, and Texas; if it rains, that work will be moved to Friday.

Sep 08, 2026 at 12:22 PM by Donelson Construction Company
Status: Planned

Resurfacing will begin this morning. Crews will prepare the streets and then start work on Blaine, Locust, and Hampton. Please remove all vehicles from these streets so we can complete the work. Expect delays and road closures; make alternate arrangements and be patient as we work to finish as quickly as possible.

Project Information
Construction Company

Donelson Construction

Create account to message contractor
Overseeing Agency

No overseeing agency specified

Create account to message agency
Project Progress
Project Code
QR Code for Project

Scan to view project details

Download QR Code